Building 5 is operational. On 2026-01-18, Building 5 overall looked like where Building 4 was on 2024-12-14. Building 4 was estimated to be operational as of 2025-10-14. So assuming a similar timeline, Building 5 will be operational by 2026-12-18.
Power (MW)
543.0
IT Power (MW)
453.0
H100-equiv
327,943
Cap-Ex ($B)
$17.36
Buildings Operational
5.0
Water (MGD)
—
Notes
Google’s New Albany data center is one of several data centers in the New Albany Business Park. We only include the buildings added or modified since 2024, when AI-specific capacity is more likely. We estimate the compute capacity primarily based on satellite and aerial imagery of the cooling towers, which are similar to towers documented at Google’s Omaha site.
- [Draft basis of air permit for Google Omaha, a similar data center](https://drive.google.com/file/d/1KN7o-wQOyt1UEud8wpM8PymXJF479r0n/view?usp=sharing)
- Google’s [2025 Environmental Report](https://sustainability.google/reports/google-2025-environmental-report/)