Building 3 is operational. Based on the stated completion date in this [regulatory filing](https://www.tdlr.texas.gov/TABS/Search/Project/TABS2026008019)
Power (MW)
238.0
IT Power (MW)
183.0
H100-equiv
208,318
Cap-Ex ($B)
$7.00
Buildings Operational
3.0
Water (MGD)
—
Notes
Meta Temple is notable for a mid-flight change in construction. A traditional H-shaped Meta data center was partially built on the site by 2023, only to be demolished in favor of Meta's new AI-optimized data center design. The power capacity of the new design was reported by construction company JE Dunn, and is backed up by our cooling model. Later, a third data center building was added to the plan. Compute capacity assumes that NVIDIA GB300 NVL72 servers are used, as these are the most popular AI chips at the time.
- [JE Dunn project page](https://jedunn.com/projects/meta-temple-data-center/) mentioning a 152 MW power capacity
- [TDLR filing](https://www.tdlr.texas.gov/TABS/Search/Project/TABS2022017728) reporting the start and end date, square footage of Building 1 and 2
- [TDLR filing](https://www.tdlr.texas.gov/TABS/Search/Project/TABS2026008019) for Building 3