Remaining Denton South buildings scheduled to complete by midyear 2026, running the full CoreWeave contracted load.
Power (MW)
366.8
IT Power (MW)
262.0
H100-equiv
252,653
Cap-Ex ($B)
$5.87
Buildings Operational
6.0
Water (MGD)
—
Notes
This Denton datacenter, currently owned by Core Scientific and formerly a bitcoin mining facility, is currently being repurposed to run AI on CoreWeave's GPUs. The contract states 260 MW total dedicated for CoreWeave, which is scheduled to finish by "Midyear 2026".
Information was primarily pulled from quarterly reports, official Core Scientific articles, among other official stakeholder materials. Satellite imagery was also utilized, but wasn't given too much weight considering the datacenter is only _partially_ contracted to CoreWeave, not the entire thing.