Start Campus - Sustainable Data Center Services, Sines, Portugal
Current Power
40 MW
H100-equivalents
31,834
Capital Cost
$1.27B
Energy Provider
—
Site Location
Tenants / Users
Microsoft #confident
Construction Timeline · 4 events
2022-01-012027-09-302027-09-30
Status
Building 2 (SIN02) projected to be operational. This is based on the timeline provided in the [factsheet](https://23712035.hs-sites.com/hubfs/SINES_02.PDF.pdf?hsCtaAttrib=199407154715) for the site. We expect VR200 GPUs to be used as a lot of those chips will have already been available in September 2027, and the "up to 600kW racks" in the factsheet suggest they are aiming for this.
Power (MW)
280.0
IT Power (MW)
233.0
H100-equiv
472,461
Cap-Ex ($B)
$8.92
Buildings Operational
2.0
Water (MGD)
—
Notes
The Start Campus Sines data campus, of which the first building is SIN01, is a data center campus in Portugal. This [six building campus is reported to be completed in 2030, with an IT capacity of 1.2 GW](https://www.startcampus.pt/sines). As of right now, only one building has been completed with the second building beginning construction. This existing building is operational and being [used to support Microsoft.](https://lp.startcampus.pt/start-campus-hosts-eus-first-nvidia-gb300-chips-with-nscale-for-microsoft)
- [Website for the site](https://www.startcampus.pt/sines)
- [Factsheet for the full site](https://23712035.hs-sites.com/hubfs/SINES%20DC_1.2%20GW%20DC%20Campus_V2.pdf?hsCtaAttrib=194868835084)
- [Article detailing Microsoft collaboration and GPU amounts](https://lp.startcampus.pt/start-campus-hosts-eus-first-nvidia-gb300-chips-with-nscale-for-microsoft)