Buildings 17-18 are operational. This is an estimate based on a rule of thumb of "operational 5 months after roof is complete", assuming the roofs took one more month after 2025-12-23.
Power (MW)
1229.0
IT Power (MW)
1024.0
H100-equiv
771,653
Cap-Ex ($B)
$39.22
Buildings Operational
18.0
Water (MGD)
21.00
Notes
Anthropic-Amazon New Carlisle is part of the Anthropic-Amazon Project Rainier collaboration. It is similar to other Amazon locations, forgoing most external cooling infrastructure in favor of direct air based cooling.
- [Air Construction Permit application for the northern portion](https://drive.google.com/file/d/1BKiTFNUk2KDaUaiHG7fz0KlkNSBTHzbb/view?usp=sharing)
- [Backup diesel generator referenced in the permit](https://www.cat.com/en_US/products/new/power-systems/electric-power/diesel-generator-sets/117341.html)
- [Announcement of Project Rainier coming online](https://www.aboutamazon.com/news/aws/aws-project-rainier-ai-trainium-chips-compute-cluster)