Building 1 operational. Estimated based on present construction progress and typical timelines.
Power (MW)
126.0
IT Power (MW)
105.0
H100-equiv
102,072
Cap-Ex ($B)
$4.00
Buildings Operational
1.0
Water (MGD)
—
Notes
Google Kansas City East is located in Missouri, and has similarities with other Google data centers like Omaha and Columbus. Currently, there is construction evidence of four buildings at the site. We estimate power capacity using satellite imagery of cooling towers. The compute capacity is based on power capacity and the energy efficiency of Google TPU chips that are available when each building becomes operational.
- [Hunt Midwest Business Center press release linking data center with Google](https://huntmidwest.com/2024/03/google-announces-1-billion-data-center-at-hunt-midwest-business-center/)
- [DCD article on the site](https://www.datacenterdynamics.com/en/news/google-files-project-plan-for-data-center-in-kansas-city-missouri/)